|
BUILDING FAME
Building Fame Photo Gallery
Preparations for the construction of FAME began in February 2002 as
Harold Burnham started carving half-hull models, working up drawings,
and hunting for wood. Thanks to the generosity of the Trustees of
Reservations, we were allowed to visit pristine Hog Island in the Essex
River and cut down spruce trees for the masts, gaffs, booms, and
bowsprit. Harold was also pleased to be able to locate some good
sources for New England white oak.
By the spring, the spruce trees had been cut down, trimmed, dragged out
of the woods, rolled down to the river, and towed upstream to the H. A.
Burnham Shipyard in Essex, across a small inlet from the Essex
Shipbuilding Museum. Two large piles of oak logs were delivered, and
their ends were promptly sealed to prevent them from drying out.
On the design front, Burnham worked his way through several drafts of
the profile and sail plan before it was time to clear out the loft of
his barn and paint the floor white for the lofting of the lines. The
repainting of the floor blotted out the lines of the THOMAS E. LANNON,
the Gloucester schooner that was built by Burnham over the winter of
1996-97.
Over the summer, Burnham completed the lofting. He also shaped and
finished the spars. The lead casting for the keel arrived in late
August and a keel-laying ceremony was held on Labor Day.
Construction began in earnest in October as the keel was pieced
together. The hefty sternpost went up on the 18th and the first frame
was raised on the 25th. By Thanksgiving there was already snow on the
ground - the forerunner of an unusually harsh winter - but most of the
frames were in place by the beginning of December.
New Year's Eve found FAME fully framed, and an evergreen bough was
placed atop the stem.
"It's not a Christmas thing, although that's what most people think,"
explained Burnham. "Whenever you finish framing a house or a boat out
of timber, you always put up a tree to thank the woods. It's a pagan
thing.
"Actually," Burnham confided, "that's the top of my Christmas tree. We
had it in inventory, so to speak, so I figured, what the heck."
Unfortunately, January was bitterly cold and the planking of the
schooner fell behind schedule. It took three months to plank FAME and
the `whiskey' or `shutter' plank, symbolizing the completion of the
process, didn't go on until March 30. An impromptu celebration broke
out at which whiskey was consumed and chanteys were sung.
April and May saw Burnham's crew swell from three to five workmen on
any given day to eight, ten or even more. The deck went on, the
stanchions went in, the engine was installed, and the hull was caulked
and faired. Away from the boatyard, work continued on the sails and
rigging.
By June, Burnham and his boatyard were in overdrive. Work went on
virtually from dawn to dusk so that the vessel could be launched on the
June tides. By June 12, the vessel was painted and ready, and Burnham
got down to the serious business of preparing to slide the 30-ton
schooner into the Essex River.
The launch itself, on June 14th, did not go smoothly. A crowd of nearly
2,000 had gathered by high tide at 11:48 AM, but FAME wouldn't budge. A
couple of times she was induced to slide a few feet toward the water,
eliciting shouts from the onlookers. But each time she stopped short.
It wasn't until nearly two hours after the high tide that Burnham and
his crew, after laboriously jacking up the bow, were able to persuade
FAME to take the water.
The schooner remained in Essex for the next few weeks as work
progressed on her systems and rigging. She made a short trip under
power to Gloucester to have her masts stepped, and was finally ready to
sail on her own on the Fourth of July. At high tide, the crew stepped
aboard, cast off her lines, and sailed her down the Essex River to the
sea.
FAME sailed first to Gloucester, where her fitting-out continued, and
then made her return to Salem on July 12th. On July 25, 2003, she
carried passengers from Pickering Wharf for the first time.
SPECIFICATIONS OF FAME
Building Fame Photo Gallery
|